Tail float almost finished

The main floats are also made of plywood attached to a frame of solid ribs. When they arrive at the workshop and are to be finished, the experience from model aircraft building comes into its own.

07.02+17.02+21.02+17.03 + 15.04 - 30.04
09/01/2025
13:56
Arvid Martinussen

The main floats are also made of plywood attached to a strong wooden frame. When they arrive at the workshop and are to be finished, the experience from model aircraft building becomes useful.

Click on the picture

© Arvid Martinussen (AM)
07.02: One more coat of varnish remains, then the tail float is finished. It will be a jewel. Good old-fashioned oil varnish has been used. None of those newfangled synthetic things.
07.02: One more coat of varnish remains, then the tail float is finished. It will be a jewel. Good old-fashioned oil varnish has been used. None of those newfangled synthetic things.
© AM
17.02 The next 3 pictures: The float is in place. The water rudder is still missing.
17.02 The next 3 pictures: The float is in place. The water rudder is still missing.
© AM
17.02
17.02
© AM
17.02
17.02
© Gunnar Koch (GK)
21.02 The aircraft has been lifted off the floor to make room for the tail float
21.02 The aircraft has been lifted off the floor to make room for the tail float
© GK
21.02 The tail section
21.02 The tail section
© AM
17.03 Ketil is working on getting the water rudder in place
17.03 Ketil is working on getting the water rudder in place
© AM
17.03 In the end it looks straight. Now the control surface remains to be attached to the rudder mechanism.
17.03 In the end it looks straight. Now the control surface remains to be attached to the rudder mechanism.
© AM
18.03 Ketil is running control cables to the rudder on the tail float. Parallel cables are also to be run to the rudder so that the two rudders move in sync.
18.03 Ketil is running control cables to the rudder on the tail float. Parallel cables are also to be run to the rudder so that the two rudders move in sync.
© AM
19.03 The rudder is to be riveted to the connection with the rudder post
19.03 The rudder is to be riveted to the connection with the rudder post
© AM
15.04 Now the water rudder is finished and ready to be connected to the controls
15.04 Now the water rudder is finished and ready to be connected to the controls
© AM
30.04 The bellcrank for the water rudder
30.04 The bellcrank for the water rudder
© AM
30.04 The transmission to the rudder
30.04 The transmission to the rudder
© AM
30.04 Rudder and water rudder connected so that they work at the same time.
30.04 Rudder and water rudder connected so that they work at the same time.